Thu, 05 Sep 2013

Estimating Tasks

As described in the previous post about our development process at GreatVines, we use LiquidPlanner for project management. Estimating how long tasks will take is important in most software development projects (and generally any project involving more than one person).

LiquidPlanner provides a great way of estimating tasks using an 80% confidence interval, but estimating tasks like this is a new concept for most developers. Below is a transcript with a developer that recently joined our project. We were able to get from "I have no idea how long it will take" to a decent estimate in about half an hour, but it should only take a minute or two for the next task.

2013-09-05 11:16:52: <Christian G. Warden> have you guys reviewed all of the
                     tasks for the september release?
2013-09-05 11:20:44: <Ben H> yes, but many of the tickets refer to parts of the
                     code I have no experience with so I have no idea how much
                     work they will be.
2013-09-05 11:23:11: <Christian G. Warden> you can put wide estimates on tasks
                     like that.  can you give me an example, and i'll walk you
                     through it?
2013-09-05 11:25:15: <Ben H> 10631525- Make Modal Form Fields scroll-able: I
                     have no idea where contacts are viewed in the application,
                     I haven't had any reason to look at their controller/model
2013-09-05 11:25:52: <Ben H> so any time estimate I would come up with would be
                     a sheer guess
2013-09-05 11:26:38: <Christian G. Warden> ok, no problem.  what's the
                     likelihood it will take you more than 2 weeks to complete
                     the task given what you currently know about the app?
2013-09-05 11:27:21: <Ben H> darn near 0% I would figure
2013-09-05 11:27:26: <Christian G. Warden> phew :) 
2013-09-05 11:27:31: <Christian G. Warden> how about 1 week?
2013-09-05 11:28:29: <Ben H> that's still very high, so 2%?
2013-09-05 11:28:38: <Christian G. Warden> how about 3 days?
2013-09-05 11:28:40: <Ben H> given that it looks like pure GUI work
2013-09-05 11:30:03: <Jim Thompson> yeah Ben the problem is that one customer
                     has put so many fields in the FieldSet that you can't see
                     the entire modal, the Save and Cancel buttons scroll below
                     the page
2013-09-05 11:30:33: <Ben H> I guess 3-4 days (if it is pure GUI work then 1-2
                     should be more then enough, unless there's something
                     unseemly complex)
2013-09-05 11:30:45: <Jim Thompson> I am going to move this task beneath the
                     Performance items Christian
2013-09-05 11:30:47: <Jim Thompson> (and Ben)
2013-09-05 11:32:20: <Christian G. Warden> would you say there's a 10%
                     probability that it will take more than 4 days?
2013-09-05 11:33:34: <Jim Thompson> at 12-32 hours it might have to drop off
                     the list, or at least to the bottom
2013-09-05 11:34:40: <Christian G. Warden> jim, we'll go through the tasks and
                     reprioritize after the estimates are updated.
2013-09-05 11:34:57: <Jim Thompson> ok, I also moved "New Task" and "New Event"
                     to October, which is when we promised it
2013-09-05 11:35:39: <Christian G. Warden> you're interrupting my estimation
                     lesson    :) 
2013-09-05 11:36:02: <Ben H> (yeah, he's been high balling for tutorial
                     purposes)
2013-09-05 11:36:11: <Jim Thompson> ok im out
2013-09-05 11:37:50: <Christian G. Warden> no, i want to come up with realistic
                     estimates.  if they're wide right now because of
                     uncertainty as to what it will take to complete them,
                     that's fine.  once we have estimates, we can decide
                     whether to invest time to come up with tighter estimates.
2013-09-05 11:38:44: <Christian G. Warden> so, do you think 4 days as a high
                     estimate is accurate?
2013-09-05 11:39:29: <Ben H> for this example I put 12-24, it's really wide and
                     most likely most of that will be learning about how that
                     GUI element is working and making the tests
2013-09-05 11:39:57: <Ben H> the range is more to show that it could go
                     horribly wrong if there is something there I have no idea
                     of
2013-09-05 11:40:24: <Ben H> but 12 still seems really high
2013-09-05 11:40:30: <Christian G. Warden> what's the likelihood that you will
                     complete the task in 2 hours?
2013-09-05 11:41:14: <Ben H> the likihood I'll complete it in 6 hours I would
                     meet the 10% threshold
2013-09-05 11:41:26: <Ben H> *likelihood
2013-09-05 11:41:38: <Christian G. Warden> ok, so, let's make it 6-24
2013-09-05 11:45:29: <Christian G. Warden> and you can check yourself by
                     imagining we're going to a casino.  you can choose from
                     two wagers:
                     1) roulette - there are 10 numbers on the roulette wheel.
                     if 1 or 10 comes up, you lose. if 2 through 8 comes up,
                     you win $100.
                     2) the bookmaker - if you complete the task in less than 6
                     hours, you lose. if you complete the task in more than 24
                     hours, you lose.  if you complete the task between 6 and
                     24 hours, you win $100. which wager do you want to take?
2013-09-05 11:47:25: <Ben H> bookmaker, it also means I can spend some
                     speculative time trying different approaches to find one
                     that solves the problem better
2013-09-05 11:47:34: <Ben H> if things go well
2013-09-05 11:49:16: <Christian G. Warden> so it's not really an 80% confidence
                     interval.  it might be more like a 90% confidence
                     interval.  you should make the range narrower.
2013-09-05 11:49:52: <Ben H> how then do you show the risk if (I doubt in this
                     case) that 10% could be really bad
2013-09-05 11:52:19: <Christian G. Warden> it's ok if there's an outlier
                     occasionally.  we want to get an accurate estimate across
                     all of the tasks.
2013-09-05 11:56:09: <Christian G. Warden> you should narrow the range until
                     you're ambivalent between taking the two wagers.  and
                     widen the range when you'd rather play roulette.
2013-09-05 11:58:02: <Christian G. Warden> but we've already gone from "i have
                     no idea how long it will take" to "i'm 90% confident, it
                     will take between 6 and 24 hours".
2013-09-05 11:59:40: <Ben H> I'm just worried it's misplaced confidence
2013-09-05 12:00:03: <Ben H> either way, given the range, I am (90%) confident
                     that I can get it done within the range
2013-09-05 12:07:07: <Christian G. Warden> nobody dies if you're wrong.  you're
                     expected to be wrong 20% of the time (once you narrow it
                     to an 80% confidence interval).  if we decide we need to
                     know with more certainty when something will be done, we
                     might ask you to spend an hour to do a little research so
                     you can come up with a tighter estimate, after which you
                     would adjust the high and/or low estimate.  for now,
                     though, estimate the tasks based on what you currently
                     know.
2013-09-05 12:07:50: <Ben H> ok

The roulette idea comes from Douglas Hubbard's How to Measure Anything.

business | Permanent Link

Thu, 08 Aug 2013

GreatVines Development Methodology

In response to a customer's request for roadmap details, and not having the project artifacts they expected based on how they manage internal projects, I've written up a description of the development methodology at GreatVines.

Axioms of Software Development

The GreatVines development methodology follows from a few high-level axioms, draws from multiple software development and project management methodologies, and makes use of modern tools for collaboration.

The axioms:

  1. Requirements Change
  2. Priorities Change
  3. Delivering Useful, Working Software Frequently Is Our Primary Goal
  4. Delivering Updates to our Software is Cheap

The first two items, changing requirements and priorities, are related, and mean that we don't expect to be able to predict the future more than a few months out. We generally have a good sense of which new features customers want to make use of next month, but not those that will be most useful next year. Additionally, as we deliver new features to customers, requirements for enhancements to these features become apparent as we get feedback from them.

Item 3, delivering quality software, stands on its own. These first three items reflect what we think are the most important principles from the Agile Manifesto.

Item 4, that the delivery of updates is cheap, follows from the fact that we are a software-as-a-service company. The days of shrink-wrapped software are gone, and updates to both our web-based and mobile applications are delivered without end-user intervention. Because delivering updates is cheap and requirements change, we are able to deliver multiple iterations of new features, and adjust requirements as we discover exactly how customers are using our software and how they would like to use it.

Therefore, we aim to deliver useful, working software frequently under the assumptions that requirements and priorities change regularly, and that delivering updates to our software does not impose a large cost on either GreatVines or our customers.

Process

We generally organize releases into three- to four-week cycles, similar to Scrum sprints, but try to keep the next two to three releases planned as well so we're looking two to three months down the road. Like scrum and kanban, we start from a backlog of features that we would like to implement. We bring together team members from development, support, implementation, and sales when prioritizing the tasks for future releases.

Each release typically has a combination of small tasks, which may already describe a combination of technical requirements and planned implementation details, and larger tasks, the requirements for which need to be further elaborated.

In preparing the bigger tasks for an upcoming release, we work to ensure the requirements are clearly defined so development can proceed. Features that require a new user interface or significant changes to an existing interface are mocked up. There are often a few iterations of mockups, as questions are raised and addressed, and the requirements and mockups updated.

Depending on the feature, we occasionally share the mockups with existing or potential customers, and solicit their input before starting development, but we generally prefer to implement a working interface, then adapt it as we get feedback from real use.

As the requirements are fleshed out, we break them down into development tasks, referencing the mockups and relevant requirements. Each task is estimated by the developer that will be responsible for writing the code.

The tasks within a release are prioritized so if there is any slippage, the highest priority tasks get completed first. The assignment of prioritized tasks to developers ensures that each developer knows which task they should be working on at any time, and helps collaboration by letting all members of the team know who is working on what and how the priorities are defined. As in kanban, it also limits the amount of work-in-progress.

During development, we try to ensure the quality of the software through developer-written tests and peer review. For both our web-based applications running on the Force.com platform, written in Apex, and our mobile app, written in javascript, we make extensive use of unit tests. Although we don't follow a test-driven development process per se, we try to take a test-first approach with bugs; for new features, we typically write tests either in parallel with implementation code or subsequent to it.

We have found that testable code is better code. If it's hard to test, it's probably poorly designed, and needs to be decomposed.

During peer review, both the tests and implementation code are reviewed. We look for areas in which the design of the software can be improved as well as ensuring that the code follows our internal coding conventions to ease future maintenance.

With our mobile app, we have started writing automated functional tests as well as unit tests. The goal is to have the tests fully specify the functionality of the application.

When a new version has been released, our release notes are updated.

Tools

There are a couple important tools we use to support our development process. We use LiquidPlanner as our project management tool. Each release is organized as a package. We have our web-based application and mobile applications organized as separate projects, broken down into broad features using folders within the projects. We pull tasks from both projects into a release package.

Mockups for new interfaces that will be built as part of the release are done at wireframe level like one would do in Balsamiq Mockups. (Our mockups are actually often done as Google Drawings because Jim typically does them, and he has somehow become proficient at creating them quickly as Google Drawings.)

The use of ranged estimates in LiquidPlanner allow us to organize releases with a fair amount of confidence in being able to hit delivery dates. Estimating software development tasks is a continuing challenge, but we find the confidence interval-based approach superior to point estimates often used in project management tools and story-point estimates used in scrum. In the backlog, we often put wide estimates on broadly defined tasks, when it's not yet clear the value of the information provided by more granular requirements and estimates. When organizing a release, we break down big tasks into smaller ones, generally around one- to six-hours. Smaller tasks are easier to estimate more accurately, and estimates improve with practice.

LiquidPlanner also serves as a collaboration tool, minimizing project management overhead. As discussed above, the priority of tasks is unambiguous. We keep estimates of remaining work on tasks up to date, and LiquidPlanner automatically updates the schedule. Discussion about task details happens within LiquidPlanner so if there's a change to or clarification of requirements, there's one place to look. (When real-time discussion is required, we generally use Google Hangouts, then record the result of the conversation in LiquidPlanner.) Using LiquidPlanner mostly eliminates the need for "what's the status?" discussions.

We also track the status of code reviews and whether the code for each task has been merged within LiquidPlanner.

We use git and GitHub for version control. Our use of github follows how most open source projects are organized. We have a greatvines organization, which contains the primary repo, from which we package our software. Each developer has a fork of the repo. Developers create feature branches for individual LiquidPlanner tasks, and open a pull request against the greatvines repo when the code is ready to be reviewed. The pull request is noted in LiquidPlanner and the task is moved to a ready-to-review package, which puts the task on hold (not scheduled for further development).

Peer review is done within GitHub, using inline comments on the open pull request. If the task needs further work, the task is moved out of the ready-to-review folder in LiquidPlanner so it's scheduled for additional work. When the pull request is merged, the task is marked done.

Future Improvements

There are a couple areas in which we are planning improvements to our development process around testing. We are using jasmine and jasmine-jquery to do some functional testing of our mobile app, but it's not exhaustive, and we don't have anything similar in place for our Visualforce interfaces. Therefore, we augment our automated testing with manual testing. We would like to add more robust automated functional/acceptance testing, perhaps using a browser automation tool like selenium or casperjs.

As we further automate testing, we also plan on introducing continuous integration. Travis CI looks promising here, with tight integration with GitHub, and extensive use among open source projects already.

There are a couple areas in which we might experiment with changes in process in the future. One is in choosing which features should go into each release. We currently use a consensus building approach in which we informally consider the value of possible enhancements to our customers. I'd like to investigate whether there might be gains to be had from the use of more formal Decision Analysis practices.

We might also experiment with scrum-style user stories for documenting requirements. For the most part, our lack of a formal requirements documentation structure has not been a problem, and we are able to turn requirements into technical designs easily. But in cases where requirements are very broadly defined, the "As a user, I want" structure may prove valuable. Using a standard structure may also ease on-boarding of new employees and coordination with any contract or outsource developers with which we work.